From Riyadh and Jeddah to Dubai, Doha and Manama, the Gulf skyline is rising faster than almost anywhere on earth. With Jeddah Tower pushing past 400 metres and a generation of supertalls anchoring our cities, the question is no longer whether active suppression and detection will perform on the day. It is whether the building itself, its compartments, its structural frame, its façades and its service penetrations, will hold the fire long enough for everyone to get out and for crews to get in. That is the job of passive fire protection.
Why high-rise is different
Fire behaves differently in tall buildings. Heat and smoke rise buoyantly through any vertical pathway, stair shafts, lift wells, service risers, and travel distances to safety are far longer. External rescue is rarely viable above the reach of aerial appliances, which top out well below the heights now permitted. Evacuation is therefore phased or defend-in-place, and those strategies only work if the building buys the time they depend on. Active systems are essential but not infallible, pumps fail, valves close, supplies are interrupted and sprinklers were never designed for façade-driven external spread. Passive fire protection (PFP) is the layer that remains when everything else is having a bad day.
What PFP actually does
PFP works on two fronts. The first is structural protection, keeping the building standing. Steel sheds roughly half its yield strength by 550°C, which a developing fire reaches in well under an hour; coatings, sprays and encasements delay that loss long enough for occupants to escape and firefighters to work beneath the structure. The required fire-resistance period, typically 90 to 180 minutes in tall buildings, is matched to the time the structure needs to survive, not the time the fire is expected to last. The second front is compartmentation, confining fire to where it started, so an incident in one tenancy or plant room cannot propagate through the building, which is what makes phased and defend-in-place strategies tenable and protects the stairs, lobbies and firefighting shafts occupants and responders rely on. Structural protection buys time for the building; compartmentation buys space within it, and a weakness in either weakens the whole.
Codes and the resilience they don’t reach
The GCC operates within a layered code environment. The UAE Fire and Life Safety Code, administered by Civil Defense, sets structural ratings, compartmentation, height and area limits and finish restrictions; SBC 801 plays the comparable role in the Kingdom under the GDCD. Both lean heavily on the NFPA family, NFPA 101, NFPA 5000, NFPA 80 for fire doors, NFPA 221 for fire walls and NFPA 285 for exterior assemblies, and increasingly cross-reference EN and BS standards. UK instruments too, the Building Safety Act 2022, Approved Document B, BS 8414/BR 135 façade testing and revised BS 8214 door guidance, shape how clients with international portfolios assure passive measures. A tower may be designed to a national code but evidenced against a basket of standards.
There is also a distinction worth holding onto. Most codes assure life safety and stop there; insurers work to a more demanding standard of property protection, captured in Estimated Maximum Loss (EML), the share of a building and its business a single fire might consume. For a 20-storey tower an insurer might write off the fire floor, two above to smoke and one below to firefighting water, an EML of 20 per cent, but only if compartmentation holds and fire cannot run up the façade or through cavities. Defeat those assumptions and credible loss climbs toward 100 per cent. On giga-project assets, where business interruption dwarfs the cost of any component, the passive package is what underwrites insurability.
Cladding: The post-Grenfell decade
No high-rise fire conversation here can avoid cladding. A succession of Emirates façade fires, and Grenfell in 2017, showed how combustible ACM panels and poorly fire-stopped cavities defeat every measure inside a building, flames climbing the exterior faster than any sprinkler can address. UAE Civil Defense has since tightened approvals, mandated re-cladding of non-compliant stock and brought façade fire-stopping into the inspection regime. The settled lesson, restated by the International Code Council, is that façades must be assessed as systems: insulation, panel, cavity, barriers and fixings together, under full-scale conditions such as NFPA 285 or BS 8414. A panel passing a small-scale test in isolation says little about how the assembly will behave on a 60-storey tower in 45-degree heat with prevailing onshore winds. The test regime is also evolving: the UK insurance sector’s RISC 501:2023 runs alongside BS 8414 but applies stricter criteria, hard-codes contested detailing such as a default penetration test and defined cavity-barrier placement, and requires results to be published openly. It is an insurer standard, not a code, and will not transfer automatically to SBC 801 or NFPA, but for international clients it increasingly defines credible façade assurance.
The Wang Fuk Court fire in Hong Kong on 26 November 2025, which claimed 168 lives across seven of eight 31-storey blocks, reopened the conversation globally. The towers were wrapped in bamboo scaffolding and combustible netting for renovation, with lift lobbies temporarily sealed in polystyrene; fire ran vertically and between blocks faster than compartmentation or crews could contain it. The lesson is direct: the temporary-works envelope of an occupied tower can defeat its permanent PFP. Nor is the risk confined to scaffolding, hot works remain a leading ignition source, and best practice now bars hot work on or above a façade while combustible elements are exposed. With the region’s stock entering its first major refit cycle, that risk is no longer theoretical.
Compartmentation in towers that never sleep
Compartmentation is only as good as its weakest penetration. A 2-hour-rated slab may be pierced hundreds of times for services, cable trays, busbars and risers, and every one needs a tested, certified fire-stop installed to the manufacturer’s system and documented, as do dampers and gap seals at slab and curtain-wall interfaces. Two factors make this demanding here. Pace: Towers rise fast, and fire-stopping is often the last item addressed and the first value-engineered. And change: A Gulf tower at half the age of its European counterpart may already have been refitted three times, each refit degrading compartmentation a little further. One asymmetry deserves attention, envelope penetrations are not controlled like internal ones, yet they are the routes by which fire breaks onto, or back off, a façade; treating them rigorously is voluntary property protection that, on a combustible façade, can decide whether spread stays contained.
Structural protection and fire doors
Intumescent coatings – thin-film paints that expand into an insulating char when heated – are the default for exposed architectural steel, with cementitious sprays where appearance is not a factor. Specification must align coating thickness with section factor and required fire-resistance period, and inspection during application is where most defects are caught or missed. Fire doors are the most frequently mis-maintained passive item: Every stair door is a life-safety device, and smoke seals, intumescent strips, self-closers, certified hardware and correct gaps are the difference between a tenable stair shaft and a chimney. The revised BS 8214 guidance and growing alignment with schemes such as Q-Mark and Certifire are pushing the industry towards documented door performance over a building’s life, not just at handover.
Where the discipline is heading
Three trends will define the discipline. Digital asset records, BIM-linked, photograph-tagged fire-stop and door registers, traceable to product certification, are moving from a nicety to a client requirement on the major giga-projects. Performance-based design is increasingly accepted for towers beyond prescriptive height envelopes, but only where the passive package is rigorously justified, not assumed. And lifecycle accountability is rising: Owners and Responsible Persons, a role now formalising across the Gulf on the UK model, are asked to evidence compartmentation’s ongoing integrity, not merely original compliance.
Closing thought
Passive fire protection rarely makes the press release when a tower tops out. It is invisible the day the building opens, and most days thereafter. But on the day a fire starts on the 30th floor – and somewhere in this region that day will come again – it is the wall that did not let the fire through, the slab penetration that held, the door that closed properly, the steel column still standing at 90 minutes and the cavity barrier that stopped the flames climbing the façade that will decide how the story ends. For those who design, specify, inspect and govern fire safety, that is reason enough to give PFP the attention it has too often had to wait for.